top of page
Building Statistics

General Information

Building Name 

      

Building Location                              

Building Occupant                      

Building Function                            

Size                                                       

Height                                                   

Number of Stories                           

Dates of Construction                   

Project Cost                                        

Project Delivery Method               

Project Owner

 

Project Architect

 

Project Contractor
 

Bridgestone Tower​

Nashville, Tennessee

Bridgestone Americas

Office

1,084,152 Square Feet

440 Feet Above Grade

32 Above Grade, 4 Below Grade

January 2015 – Mid-Late 2017

Estimated $200 Million

Design – Bid – Build

Highwoods Properties - web

Perkins + Will - web

Brasfield & Gorrie - web

Architecture

Design

 

Applicable Codes

Zoning

 

The Bridgestone Tower is of concrete and glass design with sheet music like panels extending from the sides and top of the building.

2006 IBC, IECC, IPC, IMC, IFC

2011 NEC

The building resides within Metro Nashville's Downtown Zoning Code Standards which took effect in February of 2010 and were last amended in August, 2015.  The building is located in Nashville's SoBro district.  Within this zoning requirement, the minimum setback from the planned sidewalk is 5'.  The Maximum allowed height is 30 stories, however additional height is available through Nashville's Bonus Height Program which includes LEED accreditation and underground parking.  Since this building is planned to be LEED Gold and has underground parking, extra stories were allowed.

Enclosure

Enclosure

Facade

 

Roofing

Facade is a Curtain Wall that is double paned glass  with aluminum framing. It is mounted to the Concrete and structure every Floor.

The roofing is a TPO system as shown in the detail below

Primary Systems

The Bridgestone Tower is a Design-Bid-Build project that will be completed in mid-late summer of 2017.  The site was a previous parking lot owned by the city, but was sold to Highwoods Properties for development.

The project will be closing off one of the adjacent alleys in order to have more space for material layout and office trailers.  Two tower cranes are being used in order to facilitate the high rise construction. 

The building will consist of parking in the basement as well as the first 12 floors, excluding the lobby ground floor.  The rest of the higher floors is devoted to office space that will be developed and occupied by Bridgestone Americas’ Corporate office.  The ground floor will include a lobby for the office as well as retail space.

The building is equipped with 13.8kV service from the utility.  There is also a 1500kW diesel generator located in the lower basement in the case of power failure.  There is one 15kV transformer on levels 1-11.   The first floor is also where the majority of electrical equipment is located. There are 5 transformers on level 12; 2 30kV transformers, 2 2000kV transformers, and one 15kV transformers.  There are 2 75kV transformers on levels 13-31.  The penthouse level, where most mechanical equipment is located, has 2 15kV, 2 45kV, and 2 1500kV transformers.

 

The feeders consist of both Aluminum and Copper conductors depending on the amperage.  The lower amperage feeders (15-50 amps) will mainly be copper conductors while the higher amperage (60-2,000 amps) will mainly consist of aluminum conductors.

The lighting system consists mainly of A2 fluorescents.  However, this lighting system, is only for the permit process.  The tenant (Bridgestone) will be required to detail their own lighting fit out once the building is completed and handed over after construction. 

A chilled water system is being used as the cooling system for the entirety of the building.  Most of the mechanical distribution lies within the CMU core of the building.  The major equipment is mounted on the roof penthouse level.  On the roof is the following:

  • 2 chillers for a total capacity of 1200 tons with the capacity to expand to a third chiller

  • 3 cooling towers with the capacity to expand to 4 towers

  • 2 parallel condenser pumps with the capacity to expand to 3 pumps

The system also includes several heat exchange economizers in order to reduce the use of energy for cooling.  Air distribution will be through a variable air volume system.  Each VAV box will also contain electrical heating coils for cold winter months.

The majority of the structure is reinforced concrete. This includes a concrete foundation and concrete slabs for all floors.  The floors above ground are reinforced using post tensioning techniques.  The foundation must be a minimum of 5” deep and the formwork for the columns and slabs is reused every floor.  Most reinforcing bars will be #4, #5, or #6 bars where noted for columns.  The façade system is also tied into the structure where needed.

There is also a Concrete Masonry Unit (CMU) core throughout all floors of the building that offer sheer wall stability.  This core houses the bathrooms, elevators and mechanical space for each floor.

The foundation consists of a 5’ thick slab on ground with foundation walls that form the sub-basement.  These walls will be designed to withstand at least 45PCF of active pressure and at least 330PCF of active pressure. The spread footings should be able to bear 200KSF on bearing rock.

Construction Methods

 

Electrical System

Lighting System

Mechanical System

Structural System

Support Systems

Fire Protection

Transportation

Telecommunications

The main fire protection controls are located on the ground floor.  The distribution system mirrors the mechanical system in that it goes through the core out to pendant sprinklers.  The two stairs within the core act as the main form of egress in case of fire.  The stairs will be positively pressurized at all times in order to keep them safe. 

The fire protection system will also be linked with the backup generator mentioned above.  In case of power outage due to fire, the backup generator will power the water pump in order to deliver water to areas affected by fire.

The buildings main transportation system is the 5 elevators that run throughout the height of the building within the core.  These will be accessible to those parking in the parking lot within the building as well as those working in the office spaces.  The elevators will not be accessible from the retail spaces on the ground floor.

There is also one service elevator within the building.  Also, there are two staircases on each side of the core for proper egress requirements.

Each floor contains a telecom/data room that serves as the main vein of digital information distribution throughout the building.  These rooms serve as the hubs for each floor that will spread data throughout the offices.  Because the tenant will install its own system after construction is complete, the exact details of this system are not known at this time.

bottom of page